Power engineering
- Pharmacy
- Food industry
- Power engineering
- Petrochemical industry
- Civil engineering
- Works during downtime of machines
Liptovská Mara hydroelectric power plant
23.06.2020
Liptovská Mara hydroelectric power plant
Repair of TG2 generator cooling water circular pipeline.
referencie emo 34 EN
06.12.2018
Mochovce - nuclear power plant - units 3 and 4
Completion of mechanical erection at Unit 4 of Mochovce 34 Nuclear Power Plant – erection of DN 2200 compensator
Completion of mechanical erection at Unit 4 of Mochovce 34 Nuclear Power Plant – erection of DN 2200 compensator
Confidential - Dunaj EN
29.11.2018
Confidential - Dunaj
Welding and locksmith works at construction of a bridge over Danube
Welding and locksmith works at construction of a bridge over Danube
Synthesia, a.s. Padubice
21.11.2018
Synthesia, a.s.
Welding, piping and assembly works at replacement of original boiler for a new coal burning boiler
Welding, piping and assembly works at replacement of original boiler for a new coal burning boiler
JE Mochovce 1, 2
25.10.2018
Mochovce - nuclear power plant - units 1 and 2
Execution of seismic reinforcement of emergency feedwater system
Execution of seismic reinforcement of emergency feedwater system
15.03.2017
Mochovce – nuclear power plant - units 3 and 4

Mochovce – nuclear power plant - units 3 and 4
- execution of outer sheathing by KINGSPAN panels at main production building using mounteneering equipment
- execution of outer sheathing by KINGSPAN panels at main production building using mounteneering equipment
11.07.2016

Dublin – Waste to Energy Project
Pre-fabrication of pipelines for thermal treatment plant
Pre-fabrication of pipelines for thermal treatment plant
24.06.2016
Yunus Emre (Adularya, Turecko)

Yunus Emre (Adularya, Turkey)
Yunus Emre (Adularya, Turkey) Execution of supervising activities at construction of a coal burning power plant 2x145 MW. Provision of commissioning specialists, installation of piping systems, quality control.
Yunus Emre (Adularya, Turkey) Execution of supervising activities at construction of a coal burning power plant 2x145 MW. Provision of commissioning specialists, installation of piping systems, quality control.
23.06.2016

Mondi Dynäs AB, (Väja, Sweden)
Reconstruction of regenerative boiler including the boiler body during outage in the pulp mill. Replacement of the boiler bottom and boiler body internals.
Reconstruction of regenerative boiler including the boiler body during outage in the pulp mill. Replacement of the boiler bottom and boiler body internals.
2016 - 2020 © ProfiWelders.com. All Rights Reserved. Developed by MrCode.NET